EXECUTIVE BRIEFING
Market shift: Large gas turbines once took roughly two to three years to procure; in 2026, some exceed five years.
Observed consequences: A Korean utility moved a plant’s completion target by three years. SoftBank recognised a $3.73 billion loss after revising power-equipment procurement commitments.
Decision exposure: Iraqi project sponsors must value the cost of securing manufacturing capacity against the cost of losing it and the risk of committing before financing becomes effective.
01 | The Factory Queue Has Changed
The Electric Power Research Institute describes a sharp shift in gas turbine delivery: roughly two to three years several years ago, against more than five years for some large machines by 2026. Global orders rose from 58.2 GW in 2024 to 100.3 GW in 2025, as data centres competed with utilities, industrial projects and ageing-plant replacement programmes.
Output cannot expand at the pace of order intake. Siemens Energy identified turbine blades and vanes as its principal manufacturing constraint in March 2026. Grid equipment faces similar pressure: Wood Mackenzie recorded average power-transformer lead times of 50 weeks in 2021 and 120 weeks in 2024; US generator step-up transformer lead times exceeded 160 weeks by early 2026, according to Reuters.
By September 2026, GE Vernova held 64 GW of firm gas-equipment backlog and 58 GW of reservations. Siemens Energy reported 65 GW of firm turbine backlog and 39 GW of reservations. Reservations require conversion into firm orders. The companies’ GW measures are not directly comparable.
02 | The Cost of Waiting vs Committing
In May 2026, Korea Midland Power reportedly moved the planned completion of Jeju Combined Cycle Unit 3 from 2027 to 2030. The cited reason was delayed procurement of turbines and other equipment amid global shortages. Its financial cost was not disclosed. Source: The Asia Business Daily.
Early commitments have also produced documented losses. SoftBank disclosed on 10 November 2026 that its subsidiary revised procurement plans for US data-centre power equipment, recognising a $3.73 billion loss. This included $2.85 billion in non-refundable advances and $0.88 billion for contract modifications and settlements. SoftBank attributed the charge to revised procurement plans.
Together, these cases establish a financial trade-off: later commitments can sacrifice delivery capacity; premature commitments can strand deposits.
03 | Iraq’s Unpriced Approval Window
An Iraqi precedent demonstrates the importance of financing dates. In the historical TransCanada Turbines dispute, a maintenance-services contract linked commencement to receipt of a valid, irrevocable Trade Bank of Iraq letter of credit. The precedent is limited to that contractual commencement condition.
An Iraqi contractual precedent illustrates the financing interface. Under a $60.9 million maintenance agreement signed in March 2011, TransCanada Turbines’ commencement date depended on receipt of a valid, irrevocable letter of credit from the Trade Bank of Iraq. The required instrument was completed on 23 January 2012, more than ten months after signature. The subsequent ICC award addressed unpaid sums, financial-instrument charges and performance-security disputes, ordering the Ministry of Electricity to pay approximately $4.8 million in principal. The case documents the commercial consequences of financing and contractual misalignment, although it provides no evidence of a lost manufacturing slot.
Consider a planned 2029 commercial operation date supported by a conditional OEM reservation expiring before financial effectiveness. The exposure includes the cost and availability of the replacement slot, price escalation and consequences for debt service and contractual milestones. Preserving the reservation also requires an authority legally empowered to accept cancellation risk.
Net Assessment
Before accepting a commissioning date, a project sponsor should place three documents before its investment committee: the financing-effectiveness conditions, the OEM reservation agreement and the critical-path schedule.
The committee should price two scenarios: preserving the slot through a capped, authorised commitment; and allowing it to lapse, including rebooking, escalation and delayed-operation exposure. Unsupported delivery assumptions should remain provisional.
A manufacturing slot has become an investment decision with an expiry date. Whoever controls that decision also controls part of Iraq’s future generating timetable.