Can Investors Get Paid When Turbines Sit Idle?

Who Gets Paid, Who Bears Risk?

EXECUTIVE BRIEFING | IN 60 SECONDS

  • The Evidence: Iraq commissioned approximately 5 GW through seven Independent Power Producers (IPPs) between 2018 and 2021. According to the IMF, most operated under take-or-pay arrangements and received subsidised fuel. Separately, a 2021 IMF report recorded $19.4 billion in government guarantees for IPP service payments as of June 2017.
  • The Mechanism Under Test: A private generating asset may have contractually protected revenue even when the wider electricity system faces uncertain fuel supply, dispatch constraints and weak revenue collection. This does not establish an unfair contract. It raises a question about how the associated risks are priced, allocated and financed.
  • The Decision Rule: Before approving or financing an IPP, decision-makers should establish whether public risk retention was necessary to attract investment, whether its price was justified, and whether the resulting obligations remain affordable under adverse operating conditions.

Private electricity generation can solve one problem without resolving every problem in the system that surrounds i, Iraq illustrates the distinction.

Between 2018 and 2021, seven IPPs commissioned approximately 5 GW of generation capacity, according to the IMF’s 2023 electricity-sector assessment. Most were contracted on a take-or-pay basis and received subsidised fuel from the Ministry of Oil. Yet the financial position of Iraq’s electricity sector remained strained. The IMF’s 2025 assessment reported approximately IQD 16 trillion in operating expenditure against roughly IQD 2 trillion in collected electricity revenue in 2022. These figures refer to different aspects and periods of the electricity system. They do not establish that IPP contracts caused the sector’s financial deficit. They do, however, reveal a potential tension worth investigating: the contractual obligations supporting private generation may be more predictable than the revenues available to the public electricity purchaser.

Core Question: When a generating asset remains commercially available but fuel supply or grid constraints prevent full utilisation, does the public sector receive commensurate economic value for the payment obligations and financial protections it continues to bear?

01 | BANKABILITY

A generating company can influence construction quality, maintenance, equipment efficiency and operational availability. It cannot necessarily control the upstream production of natural gas, the allocation of pipeline capacity or the public grid’s ability to accept electricity. This distinction matters in Iraq, where power generation depends on coordination across the oil, gas and electricity sectors.

The IMF’s 2023 assessment documented fuel constraints, subsidised domestic energy inputs, electricity-purchase costs and payment arrears. Its finding that the majority of IPPs operated under take-or-pay arrangements establishes the prevalence of a contractual approach, but not the precise payment triggers in any individual agreement.

A take-or-pay provision should not automatically be interpreted as payment for a service never provided. Depending on contractual terms, the purchaser may be compensating the producer for maintaining tested capacity available for dispatch, allowing the project to recover fixed costs and service its debt. The economic problem arises only if the obligation is poorly matched to the system’s capacity, the price of risk or the purchaser’s ability to pay.

Two explanations must therefore be considered together.

The efficiency hypothesis: Private developers may deliver generating capacity more effectively through procurement discipline, operational management and tighter project execution.

The risk-allocation hypothesis: Their ability to secure financing may also depend on allocating fuel, dispatch, payment or interruption risks to public counterparties better placed to manage them.

Neither explanation excludes the other. Both may contribute to the project’s commercial viability.

A third possibility is equally important: the state may deliberately retain certain risks because transferring them to investors would increase financing costs, raise tariffs or prevent the project from proceeding. The decisive test is therefore not whether the state accepted risk, but whether it accepted the appropriate risk at a defensible price, compared with feasible alternatives.

For an investment committee, this changes the first question. Instead of asking only whether a project’s PPA creates predictable revenue, it must ask what physical and fiscal conditions are required for those revenues to remain collectible.

02 | Who takes, Who pays?

Risk allocation in Iraq’s electricity sector extends beyond the PPA across three institutional functions:

  • Capacity Approval: The Ministry of Electricity procures generation capacity against anticipated demand and grid capability.
  • Molecule Control: The Ministry of Oil and associated state enterprises influence fuel availability and delivery.
  • Fiscal Underwriting: The Ministry of Finance and relevant authorities assess contingent liabilities arising from government guarantees.

These functions are linked but governed by separate instruments. A PPA establishes payment obligations, a Gas Supply Agreement (GSA) allocates fuel-delivery responsibilities, and a guarantee provides financial recourse. Their combined effectiveness depends on the physical system’s ability to supply fuel and evacuate power.

The fiscal stakes are substantial. The IMF reported approximately $19.4 billion in government guarantees for IPP service payments as of June 2017. This historical figure represents neither payments made nor current exposure, but illustrates the scale of public financial commitments.

The central question is whether the state can identify guarantee triggers, quantify potential liabilities and demonstrate sufficient fiscal capacity.

Under the World Bank’s risk-allocation principle, risks should generally rest with the party best positioned to manage them at the lowest economic cost. For Iraq, this requires joint assessment of fuel deliverability, grid capacity and contingent fiscal exposure before contractual commitments become binding.

Subscribe to receive new research notes, case studies and analysis of the decisions shaping Iraq’s energy infrastructure : Subscribe to the Newsletter

03 | THE CONTRACTUAL PILLARS

The US Department of Commerce’s Legal Guide to Investing in Power Generation in Iraq and the World Bank’s power-generation risk matrix establish a framework for assessing how fuel, construction, operational and financial risks are allocated between public authorities and private investors.

A useful precedent comes from Pakistan’s Hub Power Company (HUBCO). Its PPA distinguished payments for available generating capacity from electricity actually delivered. In October 2024, the parties agreed to terminate the 1,292 MW Hub plant’s PPA, ahead of its March 2027 expiry. The settlement addressed approximately PKR 36.5 billion in outstanding billed receivables, alongside the termination of related fuel and guarantee arrangements.

The two cases expose different stages of contractual risk: Iraq’s challenge of coordinating interconnected project obligations, and Pakistan’s experience of restructuring them after financial commitments had accumulated.

For EPC contractors and turbine OEMs, these interfaces also determine when a completed plant can be tested, accepted and paid for. Delayed fuel or grid access may defer final milestones and prolong performance-security obligations, subject to the EPC contract.

04 | THE 2026–2027 INVESTMENT WAVE

New Contracts. Old Risks. Who Learned?

In January 2026, Iraq’s Ministry of Electricity reported agreements for 48,000 MW of new generating capacity. By October, it had opened prequalification for 15-year electricity-distribution concessions across nine governorates, with parliamentary scrutiny continuing into November.

The upcoming commitments require different tests. Generation contracts depend on fuel deliverability, dispatch capability and payment security. Distribution concessions depend on measurable loss reduction, collection performance and investment delivery.

Proposed Pre-Commitment Requirements

Decision pointEvidence required before approvalContractual safeguard
Fuel supply (GSA)Verified gas quantities, pressure and transport capacityDefined shortfall liability and aligned GSA/PPA relief provisions
Capacity payments (PPA)Payment exposure at 100%, 50% and 0% dispatchIndependently verified availability, deductions and curtailment rules
Sovereign guaranteesPayment triggers, maximum exposure and collection sensitivityDefined claim conditions and fiscally supportable obligations
EPC completionFuel and grid readiness against commissioning milestonesEmployer-delay relief, alternative acceptance and security-release provisions
Distribution concessionsBaseline losses, collections and investment requirementsAuditable performance targets and remedies for missed obligations

Net Assessment

Before approving new generation contracts, the Ministry of Electricity should require a consolidated fuel–dispatch–payment model quantifying obligations under fuel interruption, grid curtailment and prolonged low utilisation. The Ministry of Finance should assess the corresponding guarantee exposure, while investors and EPC contractors test the implications for debt service, milestone payments and security release.

Each failure scenario should produce three measurable outputs: the amount payable, the contractually responsible party and the financial capacity to honour the obligation.

A Bankable Project Is Not a Resilient System.

RESEARCH NOTES & PRIMARY SOURCES

Iraq: Sector Evidence

Contractual and Comparative Frameworks

Evidence Limitation

The sector-level documents cited here do not reproduce the complete PPA, fuel-supply and guarantee schedules for each individual project. They therefore support a risk-allocation investigation, not a definitive finding about the contractual fairness or financial performance of any named producer.